Cables arrived in the middle of December and we spent the next 10 days running cable all around KamLAND. At the same time, the LED calibration system was installed. ![]() We had three crates of cables delivered to the mine. Kengo couldn't believe the amount of cables that arrived! December 15, 2000 ![]() The last crate is hoisted off of the truck December 15, 2000 ![]() Jason and Neil open the crates to unload the boxes of cables from within December 15, 2000 ![]() After freeing the boxes from the crates, they get loaded into the mine rovers for transport into the mine December 15, 2000 ![]() Kengo and Jason work together to pass down the High Voltage and Signal cables for the six PMTs on each column December 16, 2000 ![]() Jason works a cable between the scaffolding and the structure December 16, 2000 ![]() Neil and Professor Gould work on bundling the cables to the support structure for the side PMTs December 17, 2000 ![]() Neil and Jelena take up any slack in the cables before passing the slack cable up to the top level of scaffolding December 17, 2000 ![]() Neil and Jelena work to finish the bundling of cables for one column of PMTs December 17, 2000 ![]() Jason works several coils of cable along the PMT structures to one of the cable holes December 17, 2000 ![]() Neil gets ready to pass up a coil of cable through a cable hole December 17, 2000 ![]() Neil and Professor Gould pass up yet more cable through the cable hole December 17, 2000 ![]() Professor DeBraekeleer waits for more cable to be passed up December 19, 2000 ![]() In all, we passed over 500 coils of cable through two cable holes in 3 days December 19, 2000 ![]() Kengo on the top level waiting for cables from below December 19, 2000 ![]() Diane heatshrinks the connection of cables together December 19, 2000 ![]() An "A" PMT that has been installed, cabled, and heatshrunk December 19, 2000 ![]() A closeup of the "A" PMT that shows the heatshrink around the cables December 20, 2000 ![]() Jelena and Professor Gould try to find somewhere to place all the cables that have been passed up from below December 20, 2000 ![]() Finding space near one of the cable holes December 20, 2000 ![]() Neil, Kengo, and Professor DeBraekeleer hook up a set of voltage cables for PMT testing December 21, 2000 ![]() Professor Gould organizes cables to be lowered through the cable holes for the bottom level PMTs December 23, 2000 ![]() Diane lowers cable through the hole while Professor Gould looks on December 23, 2000 ![]() Organizing the cables as they come out of the cable hole will not be easy December 23, 2000 Finally, with the completion of the Tyvek installation continuing in January, only the LED calibration system needed to be installed. Click here to return to the installation process main page! Last updated: June 13, 2001 jamessim@tunl.duke.edu |